A compliant Traffic Management Plan (TMP) for underground utility excavation in Victoria must be site-specific, safety-focused, and prepared by a suitably qualified person before a single machine enters the road corridor. VicRoads guidance specifies that every TMP must include a risk assessment, clear staged diagrams covering day and night operations, proposed temporary speed limit reductions, traffic control device arrangements, and explicit provisions for pedestrians, cyclists, and people with disabilities. The plan must be available for inspection at the worksite while workers are present, per Regulation 35 of the Road Safety (Traffic Management) Regulations 2019.
When the excavation method is hydro-excavation or non-destructive digging (NDD), the TMP scope shifts in three concrete ways: the plant exclusion zone shrinks, the vacuum truck positioning must appear on every Traffic Guidance Scheme (TGS) diagram, and waste-handling documentation for EPA compliance becomes a required attachment. The coordinating road authority — VicRoads for arterial roads, the relevant local council for municipal roads — must approve the plan before works commence.
Table of Contents
- What does a compliant Victorian TMP checklist look like?
- Who should prepare and sign the TMP?
- How to prepare a TMP for underground utility excavation, step by step
- Why do TMPs get rejected, and how do you fix it?
- What are the approval timelines and cost factors in Victoria?
- How does hydro-excavation or NDD change your TMP?
- Key Takeaways
- What experienced NDD crews know about TMPs that office planners miss
- Pressureworks: specialist NDD support that strengthens your TMP
- Useful sources and further reading
What does a compliant Victorian TMP checklist look like?
VicRoads and the Road Management Act 2004 Code of Practice together define the minimum content a TMP must contain. Use the table below to map each element to the responsible party and the evidence that satisfies an assessor.
| Required element | Responsible party | Supporting evidence |
|---|---|---|
| Site-specific risk assessment | Designer / contractor | Documented hazard register, hierarchy of controls |
| Staged diagrams (day and night) | Traffic engineer / designer | Dimensioned scale drawings for each work phase |
| Traffic control device schedule | Designer / TGS preparer | Sign schedule, barrier and cone placement list |
| Temporary speed limit justification | Traffic engineer | Speed reduction memo citing AS 1742.3 values |
| Vulnerable road user provisions | Designer | Pedestrian detour route, AS 1428 compliance notes |
| Emergency access plan | Contractor / superintendent | Documented emergency egress routes |
| Worker consultation evidence | Works manager | Toolbox talk minutes, crew sign-off sheets |
| Method statement (NDD/hydro) | Contractor | Equipment list, vacuum truck specs, spoil plan |
| Permit and insurance references | Contractor | Road Opening Permit number, public liability cert |
| On-site TMP copy | Works manager | Printed and dated plan held at site |
The standards you must cite within the plan itself are AS 1742.3 (signage and delineation at roadworks), AS 1428 (access for people with disabilities), the Austroads Guide to Traffic Management (AGTTM), and the Code of Practice Worksite Safety — Traffic Management issued under the Road Management Act 2004.
A TMP is the strategic document; the TGS is its tactical execution layer. A single TMP can require dozens of site-specific TGS diagrams across a project’s life, one for each shift configuration and work phase. Never treat the TGS as a one-time attachment.
Pro Tip: Print and laminate the current TGS diagram for each shift. Assessors and WorkSafe inspectors check for the on-site copy first — a digital-only version stored on a phone does not satisfy the regulatory requirement.

Who should prepare and sign the TMP?
The person who prepares and certifies the TMP must be suitably qualified under Victorian state guidance and AS 1742.3. In practice, that means one of the following:
- A registered traffic engineer or accredited traffic management practitioner with documented experience in worksite traffic control
- A competent person with formal qualifications in traffic management and verifiable site-specific experience, where the road authority accepts this level of sign-off
- An accredited traffic management consultant, which VicRoads and most metropolitan councils require for arterial roads, long-duration works, or sites with significant public transport impact
Sign-off responsibilities do not end with the designer. The works manager or infrastructure manager must countersign to confirm the plan reflects actual site conditions. On-site, a designated Traffic Controller or Traffic Management Supervisor holds the current TGS diagram for each shift, implements device placement, and is the day-to-day compliance contact during excavation. Generic templates prepared without site-specific knowledge are frequently rejected by council assessors — the qualified person must physically understand the geometry of the site.
How to prepare a TMP for underground utility excavation, step by step
Step 1: Scope and data gathering
Collect site geometry, posted speed limits, traffic volumes (light and heavy), public transport stops, driveway sight distances, underground services records, and any environmental constraints. For NDD or hydro-excavation works, add vacuum truck access routes and spoil staging areas to this data set. A solid excavation risk assessment starts here, before any diagram is drawn.
Step 2: Site risk assessment
Follow the Code of Practice hierarchy of controls. Document clearance zones, plant proximity risks, and worker exposure periods. Produce a hazard register that covers both traffic and excavation hazards — assessors expect to see these integrated, not treated as separate documents.
Step 3: Draft TMP and TGS diagrams
Produce dimensioned, scaled drawings for each work phase, including separate day and night layouts. Select devices per AS 1742.3: calculate taper lengths and buffer distances from the posted speed, and specify physical barriers or water-filled bollards for works lasting more than a few days. Show vacuum truck positioning, spoil management zones, and safe vehicle egress on every NDD-specific TGS.

Step 4: Worker consultation and on-site review
Engaging the crews who will implement traffic control early in the planning process catches practical hazards that an office-only review misses. Run the draft past the excavation and traffic control crews, record toolbox feedback formally, and revise diagrams and SOPs before submission. Those minutes become a required attachment.
Step 5: Submit for approval
Assemble the full permit pack: the TMP and all TGS diagrams, the risk assessment, method statements, insurance certificates, and the Road Opening Permit documentation. Where works exceed four weeks, include a Construction Traffic Impact Assessment (CTIA) prepared by a qualified transport consultant — councils commonly require this for extended-duration works. Add justification for any proposed temporary speed reductions.
Step 6: Pre-works validation
Finalize TGSs for the first work phase, brief all crews, print site copies, and conduct a first-day compliance audit before opening the road corridor. For high-risk sites, schedule more frequent compliance audits and revise TGS diagrams as the site layout changes.
Why do TMPs get rejected, and how do you fix it?
Council assessors commonly reject plans that lack site-specific geometry or fail to address public transport infrastructure. The most frequent technical failures are:
- Missing dimensioned diagrams — generic layout sketches without scale or taper calculations
- Inadequate sight distances for advanced warning signage at the posted speed
- No night-time device specification (reflectivity class, lighting requirements)
- Incorrect taper lengths that do not match AS 1742.3 values for the posted speed
- No pedestrian detour route or AS 1428 compliance evidence
Process and documentation failures are equally common:
- No worker consultation minutes attached
- Plan not signed by a suitably qualified person
- Missing insurance certificate or permit reference number
- TGS diagrams absent for one or more work phases
Corrective actions are straightforward once you know the gap. Provide dimensioned diagrams with taper calculations cited to AS 1742.3, attach toolbox talk minutes with crew signatures, and confirm the certifying person’s qualifications in the plan header. Peak-hour lane closures, bus stop relocations, and works that queue traffic across intersections are the red flags that trigger Requests for Information (RFIs) — address each one proactively with a mitigation statement before the assessor asks. Councils require site-specific mitigation for public transport impacts such as bus stop relocations and documented passenger access routes.
What are the approval timelines and cost factors in Victoria?
Approval authority depends on road classification. Local councils approve TMPs for municipal roads; VicRoads and the Department of Transport and Planning handle arterial roads. The Road Opening Permit process runs in parallel and must reference the approved TMP.
Submit TMPs at least 21 days before the traffic event and allow a further 14-day review window for authority review. Late submissions cause delays and additional costs that compound quickly on time-sensitive infrastructure projects.
| Stage | Typical timeframe |
|---|---|
| TMP submission to authority | At least 21 days before works |
| Authority review period | 14 days from receipt |
| RFI response window | 5 days (pauses clock) |
| Approval and Hold Point release | 3–5 days post-RFI resolution |
| CTIA (works over 4 weeks) | Add two weeks to review |
Cost drivers include external consultant fees for TMP preparation, CTIA, and TGS drafting; Road Opening Permit fees set by the relevant authority; traffic control equipment and barrier hire; night-shift premium rates for traffic controllers; and schedule costs from plan rework after RFIs. A well-prepared first submission is the single most effective cost-control measure available to a project manager.
How does hydro-excavation or NDD change your TMP?
Choosing NDD or hydro-excavation over mechanical excavation has direct, practical consequences for TMP design. The plant exclusion zone is smaller, which often means fewer lanes need to close and pedestrian continuity is easier to maintain. That translates to different device choices, reduced detour lengths, and a lighter impact on adjacent businesses and public transport.
The TGS diagrams must reflect the NDD-specific site layout:
- Vacuum truck positioning and turning clearances shown to scale
- Spoil management and vacuum loading zones clearly delineated
- Safe vehicle egress routes for the truck between the worksite and disposal point
- Physical barriers or water-filled bollards around the excavation zone for longer-duration works
On the environmental side, NDD often reduces the need for large-scale detours, but it introduces a documentation requirement that mechanical excavation does not: where contaminated material is exposed, waste-handling records and EPA approvals must be attached to the permit pack. The environmental management obligations for spoil classification and disposal are part of the TMP’s method statement, not a separate afterthought.
Specifying NDD or hydro-excavation in the TMP from the outset gives assessors a clearer picture of the actual site footprint. A smaller exclusion zone, documented spoil management, and a vacuum truck that removes material without stockpiling it on the carriageway all reduce the perceived risk of the works — and that directly supports faster approval.
Key Takeaways
A compliant Victorian TMP for underground utility excavation requires site-specific diagrams, a documented risk assessment, suitably qualified sign-off, worker consultation evidence, and dynamic TGS updates for every work phase.
| Point | Details |
|---|---|
| Submit early | Lodge the TMP at least 21 days before works; allow 14 more days for authority review. |
| Qualify the preparer | The plan must be signed by a traffic engineer or accredited practitioner — generic templates are routinely rejected. |
| Specify the excavation method | Naming NDD or hydro-excavation up front changes staging, device selection, and waste-handling requirements in the TMP. |
| Keep TGS diagrams dynamic | A single TMP can require dozens of TGS diagrams; update them as site conditions change, not just at submission. |
| Pressureworks for NDD support | Pressureworks provides hydro-excavation and vacuum loading across Victoria, with method statements that integrate directly into TMP submissions. |
What experienced NDD crews know about TMPs that office planners miss
The most durable TMPs are written by people who have stood in the road corridor at 6 AM, not just studied the geometry on a screen. On a live excavation site, the gap between a plan that looks compliant on paper and one that actually works comes down to a few recurring details: where the vacuum truck parks when the lane is live, how spoil is staged when the pit is deeper than expected, and whether the pedestrian detour actually clears the driveway sightline at the adjacent property.
Experienced hydro-excavation crews run a pre-shift TGS check before any device goes out. They compare the printed diagram to the actual site conditions, flag any discrepancy to the works manager, and update the diagram before the shift starts — not after an incident. That feedback loop is what makes a TMP a living document rather than a filing exercise. Contractors who engage NDD specialists early in the planning process get method statements that reflect real equipment dimensions and real truck movements, which gives assessors fewer reasons to issue an RFI. The approval process moves faster when the plan describes what will actually happen on site.
Pressureworks: specialist NDD support that strengthens your TMP
Complex urban excavations, long-duration utility works, and sites with high public transport exposure are exactly where a specialist excavation partner reduces TMP risk and speeds approvals. Pressureworks delivers hydro-excavation and NDD services across Victoria, with accredited crews, EPA-licensed waste handling, and method statements written to integrate directly into your TMP submission.

Where mechanical excavation would require a large exclusion zone and extended lane closures, Pressureworks’s non-destructive digging approach reduces the site footprint, supports pedestrian continuity, and produces the vacuum truck positioning diagrams your TGS needs. The team carries the safety certifications, EPA approvals, and equipment documentation that assessors expect to see attached to a permit pack — so your submission arrives complete.
Request a project-tailored NDD quote or TMP method statement review from Pressureworks before your next submission deadline.
Useful sources and further reading
These are the authoritative references to consult and cite when preparing a TMP for underground utility excavation in Victoria:
- Road Safety (Traffic Management) Regulations 2019 — Regulation 35 defines TMP content and on-site retention requirements
- Code of Practice Worksite Safety — Traffic Management — issued under the Road Management Act 2004; sets the hierarchy of controls and TMP obligations
- VicRoads Background Paper 1 — TMP Requirements and Approval Process — mandatory content list and approval pathway
- City of Melbourne — Traffic Management Plans guidance — council submission requirements, CTIA thresholds, and common rejection reasons
- Wyndham City Council — Technical Specification Section 166 — submission lead-time guidance and permit requirements
Recommended
- Road Opening Permit Victoria: A Contractor’s Compliance Guide – Pressure Works
- Best Construction Management Software for Victorian Civil Contractors – Pressure Works
- Construction Environmental Management Plan: Victoria’s 2026 Guide – Pressure Works
- Excavation Risk Assessment: Site Manager’s Compliance Guide – Pressure Works