Before any excavation starts, assume underground services are present on the site, even if none appear on the plans. Order records through Before You Dig Australia, then positively verify locations with electronic detection and potholing or hydro excavation before mechanical plant touches the ground. Respect No Go Zones throughout, and hold a written safe system of work with a permit-to-work where the risk warrants it.
TL;DR:
- Verifying current plans for underground services is essential as records can be outdated, especially on high-risk sites with high service density or complex networks.
- Positive location through electronic detection should be followed by physical confirmation via potholing or hydro excavation to ensure safety before mechanical digging.
- No Go Zones require a minimum clearance of 300 millimeters for individuals and 500 millimeters for machinery, with specific rules for hand digging within these areas.
- Using hydro excavation for positive verification is safer and often faster than manual potholing, particularly around multiple services or in dense urban environments.
- Immediate response protocols must be followed, including isolating, reporting, and documenting any strikes or damage to underground services to prevent escalation.
Table of Contents
- Planning the Job: Site Assessment and a Safe System of Work
- How Do You Locate and Positively Identify Underground Services?
- No Go Zones: How Close Can You Dig to a Buried Service?
- Choosing the Right Excavation Method Near Buried Services
- Permits and Record Searches: What Paperwork Comes First?
- What to Do If You Strike an Underground Service
- Who Is Responsible for Safety Near Underground Services?
- Quick Checklist Before Any Excavation Begins
- What Non-Destructive Excavation Projects Actually Teach You
- Get Positive Verification Before You Dig
- Sources
Planning the Job: Site Assessment and a Safe System of Work
Every safe excavation starts on paper, not with a digger bucket, relying on a safe excavation process to manage risks effectively. Define the scope, the excavation method, the timeline, and any site constraints (traffic, access, nearby structures) before crews mobilize. Lodge record searches early as utility owners may take some time to respond, and a rushed timeline is how crews end up guessing at depths instead of confirming them.
A written safe system of work should cover:
- The scope of works and excavation method chosen for each stage
- Named supervisors, competent operators, and their specific responsibilities
- Required PPE and site-specific controls
- Emergency contact details for utility owners and emergency services
- Conditions triggering a stop-work decision
WorkSafe Victoria frames the safe system of work around three pillars: planning, locating and identifying services, and safe digging practices such as non-destructive excavation. Even genuine emergency repairs don’t get a pass on this logic. If records can’t be pulled in time, treat every service as live and dig accordingly.
How Do You Locate and Positively Identify Underground Services?
Plans tell you where a service was installed, not necessarily where it sits today. Positive locating closes that gap through three stages:
- Request records. Lodge a Before You Dig Australia enquiry and request current plans from every listed asset owner. Ausgrid requires cable plans no older than 30 days before excavation begins, a rule worth building into your project calendar rather than discovering at the last minute.
- Run electronic detection. Cable and pipe locators read signal and tracer wires, but ambiguous readings near clustered services or degraded tracer wires are common. Treat a clean scan as a starting point, not a guarantee.
- Verify physically. Hand potholing or vacuum and hydro excavation confirms depth and alignment where detection is uncertain or the consequence of a strike is severe.
Plans go out of date fast. Regrading, resurfacing, and previous repairs shift the real depth of a line without anyone updating the record, and cross-boring between unrelated services is a known failure mode on older networks.
Pro Tip: Treat a “confirmed clear” reading from a locator as provisional until a hand-dug or vacuum-excavated pothole backs it up. Signal readings can miss plastic gas lines and de-energized cables entirely.
No Go Zones: How Close Can You Dig to a Buried Service?
No Go Zones exist to stop plant and people from closing in on a service before it’s confirmed safe to approach. The standard guidance sets a buffer of 300 millimeters for individuals and 500 millimeters for plant, and service owners can require wider clearances for high-voltage cable or pressurized pipeline.
Hand digging inside a No Go Zone follows its own rules:
- Use curved-edge spades and controlled foot pressure rather than picks or power tools
- Expose services from the side, not directly from above, to reduce the chance of piercing a sheath
- Stop and reassess if soil conditions or buried debris make hand tools impractical
Mechanical plant should only enter a No Go Zone after confirming services are clear or protected, with appropriate controls and supervision. Planning the trench line to route around known services, rather than straight through them, avoids exposing something you didn’t need to touch.
Choosing the Right Excavation Method Near Buried Services
Not every excavation method belongs on every site. Hand potholing suits small, low-risk exposures where a single service needs confirming. Hydro and vacuum excavation earns its place when soil is compact, the service density is high, or the consequence of a strike (a high-voltage cable, a gas main) makes precision non-negotiable.
- Hydro excavation can be used to expose services with less impact to surrounding soil compared to mechanical digging
- It performs well in clay and compacted fill where hand tools slow progress to a crawl
- Competent operators with proper training and calibrated equipment help protect underground assets during excavation
- While hydro excavation may cost more per meter than mechanical digging, it can reduce risks of costly strikes and associated consequences
Crews using hydro excavation for positive verification typically get a cleaner, faster expose than manual potholing on tight urban sites, particularly where several services run close together.
Permits and Record Searches: What Paperwork Comes First?
Before mobilizing plant, close out the administrative steps that make the physical work defensible if something goes wrong.
- Lodge a Before You Dig Australia enquiry for every relevant utility, and confirm plan currency against the asset owner’s own timing rules.
- Secure a permit-to-work where the job involves high-voltage cable, gas mains, or any excavation inside a No Go Zone. The supervisor issuing it should sign off only once locate results are on file.
- Keep mark-out records, potholing confirmation notes, and any service-owner conditions on site, not in someone’s inbox.
Requirements shift by state regulator and by service owner, so always check the applicable rules for your project’s jurisdiction rather than assuming last year’s process still applies.
What to Do If You Strike an Underground Service
A strike changes the job in seconds. For electrical contact, stay on or in the machine unless fire or immediate danger forces evacuation, and call the utility and emergency services before anyone approaches the equipment. For a gas escape, evacuate the area, eliminate ignition sources (no phones, no engines running), and notify the utility immediately.
- Isolate the area and stop work on that section entirely
- Report the strike to the service owner and preserve the scene for their investigation
- Record what happened, when, and under what conditions, per your company’s incident procedure and Safe Work Australia reporting expectations
Who Is Responsible for Safety Near Underground Services?
Employers are responsible for risk assessment, training, and ensuring subcontractor crews are competent in practice as well as in credentials.
- Supervisors and operators need working knowledge of detection tools, correct PPE, and safe digging methods, not just a toolbox talk memory of them
- Spotters and permit-to-work signoffs stay active for the life of the job, since ground conditions and exposed services can change what’s safe hour to hour
- Toolbox talks and training records document that competence, which matters as much for regulator audits as for day-to-day safety
Quick Checklist Before Any Excavation Begins
- Records ordered, current, and reviewed against the site
- Positive locate completed via detection and potholing or hydro excavation
- Permit-to-work issued where required
- Trained crew and supervisor on site, emergency contacts confirmed
- If any of the above is missing, stop. Escalate instead of reaching for mechanical plant.
Pro Tip: When timelines are tight and the service density is high, call in specialist non-destructive excavation support rather than pushing a mechanical dig to save a day. One strike costs more than the delay ever would.
What Non-Destructive Excavation Projects Actually Teach You
Plans lie more often than crews expect, not out of negligence but because ground shifts, gets repaired, and gets rebuilt over decades. The recurring failure isn’t reckless digging. It’s trusting a record that hasn’t matched reality in years. Paying for non-destructive verification on a high-risk service almost always costs less than the delay, repair, and reporting that follow a strike. The teams that avoid strikes are rarely the fastest ones. They’re the ones that stopped and re-verified when something didn’t line up with the plan.
— MYBMC
Get Positive Verification Before You Dig
Pressureworks gives Victorian crews a faster path to positive locating than hand potholing alone, without the risk of a mechanical strike on a service that wasn’t where the plan said it would be. Our hydro excavation and vacuum loading crews expose services precisely, protect coatings and tracer wires, and hand back a marked, verified site ready for permit-to-work sign-off.

Call Pressureworks when tolerances are tight, the service is high-consequence, or the timeline doesn’t allow for trial and error. You’ll get an on-site verification report, clearly marked locations, and support documenting the job for your permit-to-work file. For projects near Geelong, our Geelong hydro excavation team covers the same non-destructive standard. Get in touch to scope your next excavation before the first shovel goes in.
Sources
- Guide to undertaking work near underground services | WorkSafe Victoria
- Guidebook for undertaking work near underground services (Energy Safe Victoria / WorkSafe Victoria)
- Working near underground cables | Ausgrid
- General guide for working in the vicinity of overhead and underground electric lines | Safe Work Australia